Superior Contracting Services LLC
Woburn, MA 01801
Featured Project Return to Projects List
Miraca Life Sciences
Project Information
- Project Location:
- Needham, MA
- Approx Contract:
- $80,000
- Status:
- Completed - Aug 2017
- Structure Type:
- Laboratory
References
- Owner:
- Miraca Life Sciences
- General Contractor:
- J Calnan & Associates
- Client:
- Brian Mikolaycik - Senior Project Manager J Calnan & Associates
Scope Of Work
Superior Contracting PM: Thomas Walker
Scope: Removal and disposal of CMU walls, carpet/CVT/tile flooring and base, GWB partitions, doors, and frames, soffit/hard ceiling on 2nd floor, ramp and step, chimney, laminate window sills, etc. All concrete scope including cutting, removal, excavation, and re-pour is excluded.