Marina Pump Station

Project Information

Project Location:
MT
Approx Contract:
$5,000,000
Status:
Completed
Structure Type:
Gas Station

References

Client:
City of Saratoga Springs

Scope Of Work

This project consisted of installing 1200 Linear Feet (LF) of 30-inch ductile iron pipe and 100 LF of 42-inch HDPE, dredging of the marina, as well as part of the lake and constructing settling ponds for the dredged material. The project also included 37-foot-deep excavation for a wet well and 25-foot-deep excavation of the 42 inch HDPE.

COP also constructed a new pump station consisting of four new 10 inch pumps with mechanical pipe, including two self-cleaning amiad filters. A new intake structure, with 30-inch SS wire screens and air burst systems, was also installed.

DURATION: 12 months

COST: $5,318,491

Project Images

#
#
#
Share URL copied!
https://www.thebluebook.com/iProView/1321443/cop-construction-llc/subcontractors/
Facebook
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.