505 Herndon Square - Thru-Wall Flashing
Project Information
- Project Location:
- Herndon, VA
- Status:
- Completed
- Structure Type:
- Misc Project
References
- Owner:
- BECO Management
- Architect:
- Not Provided
- General Contractor:
- Not Provided
Scope Of Work
SCOPE OF WORK FOR THRU-WALL FLASHING
-
- Mobilize material, labor and equipment to job site.
-
- Set Up swing stage and move as needed to perform the flashing work at the 6 balcony areas.
-
- Remove one row of decorative block, clean and set aside for reuse.
-
- Using Wire wheel clean off all deterioration and rust on metal lintels.
-
- Coat lentils with rust inhibitor paint.
-
- Install thru wall flashing using Perma Barrier, mastic, end dams and termination bar; 248 linear
feet total for all 6 balconies.
NOTE: The new flashing will overlap with the existing vinyl membrane.
-
- Replace decorative block matching mortar as close as possible to existing
-
- Demobilize and remove all job related debris from site.
SCOPE OF WORK FOR GLASS TO METAL SEALANTS, WINDOW PERIMETER AND CONTROL JOINT SEALANTS
-
- At all windows except for those previously repaired, cut back gaskets if needed and/or remove deteriorated sealants if present.
-
- Wipe area clean with alcohol to receive new silicone glazing.
-
- Install Dow Corning 795 Black silicone creating a 45 degree cant joint at glass to metal locations.
-
- At window perimeters on the first and second floor and at both entrances, remove old and
deteriorated sealants and discard off site.
-
- Prep areas to receive new urethane sealant by cleaning free of dust , dirt and debris.
-
- Install the appropriate primer, backer-rod and NP1 urethane sealant. Tool all joints per industry
standards.
-
- At all vertical control joints (except what has been replaced above the third floor), remove old
and deteriorated sealants and discard off site.
-
- Prep areas to receive new urethane sealant by cleaning free of dust, dirt and debris.
-
- Install the appropriate primer, backer-rod and NP1 urethane sealant. Tool all joints per industry
standards.
-
- Demobilize and remove all job related debris from site.