Farley Pavilion Electrical Room Upgrade

Project Information

Project Location:
Boston, MA
Status:
Completed
Structure Type:
Misc Project

Scope Of Work

In February 2012, Mass. Electric Construction Co. began the replacement of the electrical distribution feeding the Farley and Pavilion Buildings at Children’s Hospital Medical Center (CHMC) in Boston, Mass. The project was required to increase the efficiency of the system and addressed updates to electrical code.

The original project was scheduled for a year, but with added scope and the challenge of shutting down equipment in an active hospital, the schedule was extended to twenty-two months. The work consisted of removing the existing equipment, which included:

7 switchboards

3 oil filled transformers

4 dry type transformers

a G&W Switch

old panel boards, and

all the old existing feeders

The new installation included installing 3 new switchboards, 6 ATS switches, 2 – 1500kva oil filled triplex transformers, new G&W switches, 19 new panels and new feeders in MI cable, pipe and wire and bus duct. The transformers run on FR3 fluid, which is environmentally friendly and runs cooler than oil. The transformers also have their own built in oil containment pans.

MEC worked closely with the hospital and engineer to identify changes to the project to improve the end product. This quality project was completed with zero safety incidents.

Share URL copied!
https://www.thebluebook.com/iProView/1300286/mass-electric-construction-co/subcontractors/
Facebook
X
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.