Featured Project

Cumberland Farms

Monroe , NY
Scope Of Work:

Site work for new Cumberland Farms gas station on 1 acre site

Services Provided:

  • Site demolition including demolition of remaining garage building
  • Processed and crushed all concrete and asphalt on-site and reused for parking lot base material
  • Excavation and grading 
  • Excavation and backfill of 5,000 SF store
  • Excavation for (2) 15,000 gallon fuel tanks, 16 feet deep
  • Storm drainage systems
  • Sanitary sewer connection 
  • Granite curbing
  • Fine grading of parking lot

6 month duration 

Approx Contract: $400,000
Completion: May 2018