Featured Project Return to Projects List
Temescal Canyon
Project Information
- Project Location:
- Corona, CA
- Status:
- Completed
- Structure Type:
- Retail Store
Scope Of Work
Sitting right off of the 91 Freeway in Corona, California lies a 7-acre site that was designed to accommodate a standard distribution building. Although the earthwork was relatively straight forward with 50,000 cu. yrds. of materials to be excavated one particular objective that made this project stand out from the rest was a sizable retaining. This 17ft retaining wall was designed by the engineers to protect the site from slides that can occur in the foothills which wrap around the western side of the site. This type of special requirement was no problem for the Earth Basics team!
Notable Equipment Used: (4) 623 Caterpillar Scrapers, (1) Caterpillar 824 Cat Dozer, (1) John Deere 750K Dozer, (1) John Deere 772 Blade, (1) John Deere 450 Excavator, (1) Caterpillar 950 Loader, (1) Gradall (1) 4K Water Truck