Finley completed a parking lot repair project in Burke, VA, making the existing asphalt parking area more durable, smooth and easy to navigate.

During our site visit we determined that the elevations needed to be adjusted and that the condition of the sub grade needed adjustments. The client also wanted to have a new curb and gutter installed.

Our crew started by first removing the existing layer of pavement. The subgrade was in fact in poor condition so we applied the FDR method (full depth reclamation), mixing the existing subgrade with cement to a depth of 12 inches. We then compacted the new surface down, giving us a solid base to work with. Once the base was prepared, we installed a 2.5-inch base layer and a 1.5” surface course layer of asphalt.