Riverbank Stabilization at Valley Railway MP 53.78
Project Information
- Project Location:
- Brecksville, OH
- Approx Contract:
- $200,000
- Status:
- Completed
- Structure Type:
- Misc Project
Scope Of Work
DESCRIPTION OF WORK: Work consisted of site preparation. Individual trees were removed as well as debris. The bank was excavated. Shoulder Ballast was replaced. Channel protection stone B and C was placed as well as AASHTO M-57 stone and turf reinforcing mat type 1. Select fill and topsoil added. Everything was seeded, fertilized, and mulched. Dormant live stakes were also placed at the end of the project.
Total Contract Amount: $190,716.70