Featured Project Return to Projects List
Woodward Road Repair Sinkholes by Pad 602 Culvert Naval Base Point Loma
Project Information
- Project Location:
- CA
- Approx Contract:
- $250,000
- Status:
- Completed - Jan 2020
- Structure Type:
- Government
References
- Owner:
- NAVFAC Southwest, Naval Base, Point Loma
Scope Of Work
Design/Build Project
Demolished existing headwall and k-rail.
Excavated soil/sediment buildup to existing flow line (250 Cubic Yards)
Constructed new headwall with wing walls.
Installed concrete pad at upstream culvert.
Installed riprap at downstream culvert.
Installed bollards with galvanized cable on each side of headwall.
Filled existing sinkholes and regraded slopes.
Gabion baskets were provided for permanent erosion.
Steam-cured PVC lining was provided inside two 30” diameter culverts.