Featured Project Return to Projects List
Signage Rollout
Project Information
- Project Location:
- National
- Approx Contract:
- $18,000
- Status:
- Completed - Feb 2016
- Structure Type:
- Retail Store
References
- Owner:
- ACE Cash Express
- Client:
- David Wilkerson Ace Cash Express
Scope Of Work
We even do the smaller projects.
Here we were asked to provide a large scale Signage install rollout for Ace.
In 2015 we completed 330 sites completed in 12 weeks using 2 guys.
In 2016 we completed 260 sites for them in 6 weeks using 2 guys.