Featured Project Return to Projects List
William J. Nealon Federal Building – Hvac Modifications And Re-roof
Project Information
- Project Location:
- PA
- Approx Contract:
- $2,000,000
- Status:
- Completed
- Structure Type:
- Government
Scope Of Work
The JD Bravo Company (Bravo) was selected by the GSA Region 3 to complete a bid-build replacement of three cooling towers and a design-build for the replacement of the building’s condenser water piping and a design-build roof replacement of the cooling tower area roof.
Bravo assembled a team of mechanical subcontractors, engineers, and various trades to work with the GSA field personnel and regional team to complete this challenging project.
Notable features of this project include:
The historic designation of the Nealon US Courthouse created significant challenges in the establishment and design and installation of new condenser water piping.
By special request of the GSA, the mechanical portion of this project is expected to be delivered three months ahead of schedule in time to support the 2020 cooling season.
The project is anticipated to be completed within its $1.85 million contract price.