Featured Project Return to Projects List
International Big Bore Diesel Engine Assembly Plant
Project Information
- Project Location:
- Huntsville, AL
- Status:
- Completed
- Structure Type:
- Manufacturing Plant
References
- Owner:
- International Truck and Engine Corporation
- Architect:
- Gresham, Smith and Partners
Scope Of Work
The project consisted of a new 300,000-square-foot facility, of which 10,000 square feet serves as a main office area. The project also included a new parking lot and a large concrete paving area around the facility for truck parking and deliveries.
With an aggressive six month schedule and a two month owner delay, Doster worked nights and weekends to meet production expectations.