Upper Chesapeake Medical Center

Project Information

Project Location:
Bel Air, MD
Approx Contract:
$8,000,000
Status:
Completed - Jan 2014
Structure Type:
Hospital / Nursing Home

Scope Of Work

A 2 MW Trigeneration System to Optimize Energy Performance

 in Bel Air, Maryland, the Upper Chesapeake Medical Center was home to an aging energy system that wasn’t optimized for the hospital’s usage or prepared to support growth. CMTA brought decades of experience to bear and designed a Trigeneration system (CHP), producing cooling, heat, and power from a single fuel source.

THE CHALLENGES

Integrating CHP into the operating hospital central plant (hot water, steam and chilled water systems)

Integrating CHP into the operating hospital electrical distribution (normal and emergency power systems)

The hospital required additional cooling capacity with no capital expenditure

THE SOLUTIONS

The system was optimized to provide the best economic payback for the system owner, who executed a Power Purchase Agreement with the host facility (UCMC). This process involved measuring and collecting energy consumption data at the facility over the course of the project development process. This data was used in the development of an energy simulation to predict potential production values for the system. CMTA developed the simulation and software in-house as commercially available software was not deemed flexible enough to allow some of the innovative strategies that were examined and eventually included in the final design. The system has historically produced 10-13 million kWh annually and is predicted to deliver over $9 million of savings over the course of its service life.

The power generator and heat recovery steam generator were paired with a multi-energy absorption chiller to provide additional cooling capacity at the facility’s central plant. The chiller helps fill voids in the hot water demand that might otherwise result in the engine wasting jacket water heat and provides the hospital with an additional 350 tons of cooling that allows the central plant to  the entire facility peak demand without one of the electric chillers. Prior to the addition of the absorption chiller, the plant was struggling to keep up with increasing chilled water demand without sacrificing equipment redundancy.

The system employs an electrical load-following scheme that sets it apart from similar projects. This control scheme was carefully studied and scrutinized during the design to ensure that the extra investment in capacity would  the owner efficiently. The load-following sequence modulates the system output in response to real-time electrical and thermal demand data to produce as much energy as possible, without exceeding what the facility requires.

Project Images

#
#
#
Share URL copied!