Featured Project Return to Projects List
MSU North Campus Infrastructure
Project Information
- Project Location:
- OH
- Status:
- Completed
- Structure Type:
- Misc Project
References
- Architect:
- FTC and H
Scope Of Work
COST:
Total – $44.9 million
Phase 1 – $15.9 million
Phase 2 – $11 million
Phase 3 – $10 million
Phase 4 – $8 million
:
CM At-Risk (with limited self-perform concrete)
Granger was selected to perform 2012 North Campus Infrastructure which involved renovation reconstruction existing steam utility system within MSU’s historic North Campus. Based on ’s exemplary within an extremely aggressive , MSU hired Granger to also perform remaining 3 phases . included removal replacement high pressure low pressure steam piping, electrical communication vaults ductbank, cast--place precast steam tunnels vaults, sanitary sewer, storm sewer watermain as well as reconstruction roadways sidewalks.
Phase 1 (2012):
Electric Ductbank: 2502 LF
Telecom Ductbank: 3634 LF
Steam: 2577 LF
Crawl Tunnel: 591 LF
Walk Tunnel: 1986 LF
Steam Vaults: 8
Water: 4257 LF
Chilled Water: 100 LF
Storm: 2385 LF
Sewer: 815 LF
Start: Jan. 2012
Completion: Aug. 2012
Phase 2 (2013):
Electric Ductbank: 1173 LF
Telecom Ductbank: 1000 LF
Steam: 1444 LF
Crawl Tunnel: 211 LF
Walk Tunnel: 1234 LF
Steam Vaults: 7
Water: 4069 LF
Chilled Water: 628 LF
Storm: 802 LF
Sewer: 975LF
Start: Dec. 2012
Completion: Oct. 2013
Phase 3 (2014):
Electric Ductbank: 800 LF
Telecom Ductbank: 100 LF
Steam: 1500 LF
Crawl Tunnel: 730 LF
Walk Tunnel: 400 LF
Steam Vaults: 9
Water: 2000 LF
Chilled Water: 440 LF
Storm: 950 LF
Sewer: 300 LF
Start: Dec. 2013
Completion: Nov. 2014
Phase 4 (2015):
Electric Ductbank: 550 LF
Telecom Ductbank: 180 LF
Steam 550 LF
Crawl Tunnel: 350 LF
Walk Tunnel: 200 LF
Steam Vaults: 4
Water: 990 LF
Chilled Water: 628 LF
Storm: 850 LF
Sewer: 590LF
Start: Feb. 2015
Completion: Aug. 2015