MSU North Campus Infrastructure

Project Information

Project Location:
OH
Status:
Completed
Structure Type:
Misc Project

References

Architect:
FTC and H

Scope Of Work

COST:
Total – $44.9 million
Phase 1 – $15.9 million
Phase 2 – $11 million
Phase 3 – $10 million
Phase 4 – $8 million

:
CM At-Risk (with limited self-perform concrete)

Granger was selected to perform 2012 North Campus Infrastructure which involved renovation reconstruction existing steam utility system within MSU’s historic North Campus. Based on ’s exemplary within an extremely aggressive , MSU hired Granger to also perform remaining 3 phases . included removal replacement high pressure low pressure steam piping, electrical communication vaults ductbank, cast--place precast steam tunnels vaults, sanitary sewer, storm sewer watermain as well as reconstruction roadways sidewalks.

Phase 1 (2012):

Electric Ductbank: 2502 LF

Telecom Ductbank: 3634 LF

Steam: 2577 LF

Crawl Tunnel: 591 LF

Walk Tunnel: 1986 LF

Steam Vaults: 8

Water: 4257 LF

Chilled Water: 100 LF

Storm: 2385 LF

Sewer: 815 LF

Start: Jan. 2012
Completion: Aug. 2012                 

Phase 2 (2013):

Electric Ductbank: 1173 LF

Telecom Ductbank: 1000 LF

Steam: 1444 LF

Crawl Tunnel: 211 LF

Walk Tunnel: 1234 LF

Steam Vaults: 7

Water: 4069 LF

Chilled Water: 628 LF

Storm: 802 LF

Sewer: 975LF

Start: Dec. 2012
Completion: Oct. 2013                

Phase 3 (2014):

Electric Ductbank: 800 LF

Telecom Ductbank: 100 LF

Steam: 1500 LF

Crawl Tunnel: 730 LF

Walk Tunnel: 400 LF

Steam Vaults: 9

Water: 2000 LF

Chilled Water: 440 LF

Storm: 950 LF

Sewer: 300 LF

Start: Dec. 2013
Completion: Nov. 2014

Phase 4 (2015):

Electric Ductbank: 550 LF

Telecom Ductbank: 180 LF

Steam 550 LF

Crawl Tunnel: 350 LF

Walk Tunnel: 200 LF

Steam Vaults: 4

Water: 990 LF

Chilled Water: 628 LF

Storm: 850 LF

Sewer: 590LF

Start: Feb. 2015
Completion: Aug. 2015

Share URL copied!
https://www.thebluebook.com/iProView/1528625/granger-construction-company/general-contractors/
Facebook
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.