Pileworks
Magnolia, TX 77355
Featured Project Return to Projects List
Radar Site Installation
Project Information
- Project Location:
- Toolik Lake, AL
- Status:
- Completed
- Structure Type:
- Misc Project
Scope Of Work
Project: | Toolik Lake Radar Site Foundation |
Installation Criteria: | 400 ea. Drilled and Cased Micropile |
Project Lead: | Tom DePeter |
Equipment: | Cat 320 and HD50 |
Installation Depths: | 10′ to 25′ |
Jobsite Restrictions: | Remote work area, Environmental concerns with large footprint equipment. |
Geotechnical Concerns: | Dense Continuous Rock, Frozen Clays and Tundra. |
APE supplied: | Built Custom Drill Tooling used to Drill through solid rock and Frozen soils |
Time to Install single unit: | 10 Minutes to drill with Down-the-hole Hammer, each location |
APE job influence: | Designed Drilling system to run air tools that can be run on smaller excavators |
Description: | With -40 below and miles from the nearest town not being a big enough challenge already, Onyx undertook this project on with a stride that carried them all the way to project completion 3 weeks ahead of schedule. |
A month prior to the Project start date APE set out the build a smaller, lighter platform drilling configuration that would allow the contractor to utilize a wide array of drill tooling. | |
With no ice roads to work from,this configuration insured that minimal environmental damages would occur while running on top of the sensitive tundra. |