Featured Project Return to Projects List
Public School 32 – Floor Replacement/Boiler Room/Climate Control & Heating Plant Upgrade
Project Information
- Project Location:
- Bronx, NY
- Approx Contract:
- $20,000,000
- Status:
- Completed - Dec 2013
- Structure Type:
- School / College / University
References
- Owner:
- New York City School Construction Authority
- Architect:
- Kenny & Khan Architects
Scope Of Work
The scope of work includes design-build of a 2,000 square foot space including temporary kitchen, bathroom facilities and hallway to accommodate the complete first floor structures’ replacement with a multi-phase schedule to facilitate the building occupants. The project also consists of replacement of the boiler plant, temperature control systems, MEP demolition, installation of a sprinkler system, fire alarm upgrades, new bathrooms and a new kitchen.