Scope Of Work
This project involved The demolition of a former Marsh Super Store, partial demolition of a adjacent strip mall and selective demolition of the canopy that remained to make way for construction of a New Kroger Marketplace Building (Demo of Steel Frame masonry construction structure)
Phase 1 Demolition of the former Marsh Store. Completed on time and within budget. Included removal of structure, slab, footers and column pads
Phase 2 Partial demolition of the existing strip mall. Completed on time and within budget. Included precise saw cutting of the structure at the separation point, shoring of the structural I-Beams on both sides of the separation point to prevent uncontrolled collapse of structure of the structure that was to be demo'd and stabilization of the structure that was to remain
Phase 3 Partial demolition of the canopy on the structure that remained to project specifications
Beach completed this project within all project specifications including all Owner/General Contractor requests as well as Gray area requests
Project completed EARLY at request of Owner/General Contractor