Insight Phase I
Project Information
- Project Location:
- St. Paul, MN
- Status:
- Completed - Sep 2013
- Structure Type:
- Storage Facility / Warehouse
References
- Owner:
- Instaight
- Architect:
- N/A
- General Contractor:
- Jepsen
Scope Of Work
This job started as an emergency shoring job. We were called after one of the wood bolsters failed causing the wood column then to fail. The floors had dropped 10 to 12 inches. We evaluated the whole building after collapsed area was shored up discovering there was 80 plus columns and bolsters failing in the building. The first phase total weight shored and lift was over 1400 tons.
We designed, supplied, and install the shoring and lifting and did all structural repairs.