Taxiway Extension - MCAS
Project Information
- Project Location:
- Beaufort, SC
- Approx Contract:
- $250,000
- Status:
- Completed
- Structure Type:
- Sewage / Water Treatment Plant
Scope Of Work
Our Navy contract was delayed as a result of a defective design that required a redesign in order to comply with environmental requirements as set forth by South Carolina DHEC. The redesign effort came in iterations of responses to sixty (60) RFI and twenty (20) contract modifications. Our believed that they were entitled to remuneration for delay and estimated the amount at approximately $ 250,000. AB Consulting prepared a REA after reviewing all the documentation. The REA included CPM scheduling proofs, CPM frag-nets, analysis, man-hour curves, delay narrative. AB Consulting participated in direct settlement negotiations with the Contracting Officer. We recovered $ 600,000 for our .