Mansfield Hollow Hydro

Project Information

Project Location:
Mansfield, CT
Status:
Completed - Dec 2013
Structure Type:
Renewable Energy

Scope Of Work

Under contract to O’Connell’s Energy Group, Sealand Enviro constructed a 500 KW – Hydroelectric Project adjacent to the U.S. Army Corps of Engineers – Mansfield Hollow Dam which lies on the confluence of the Natchaug, Fenton and Mt. Hope rivers in Mansfield, Connecticut. Sealand Enviro substantially completed this project within an accelerated 6-month schedule and ahead of the target completion date – December 2013