Pump & Meter Service, Inc.
Hopkins, MN 55343
Featured Project Return to Projects List
Penske Truck
Project Information
- Project Location:
- Brooklyn Park, MN
- Approx Contract:
- $300,000
- Status:
- Completed - Nov 2019
- Structure Type:
- Misc Project
References
- Owner:
- Penske Truck
Scope Of Work
Removals and Tank Restoration
Fuel System Installation Equipment
Qty Description
1 Wall Hydrant
12 Bollard Covers/Sleeves
1 JE Adams Vacuum
4 Riverside S/S Island Forms 4’x6’x13”
7 4” Clean Outs
12 8” Bollards
2 6’x7’ Steel Post for lube racks
4 Collection boxes
Canopy Downspouts
Fuel System Installation
Description
• Prep excavation for (1) 20,000-gallon UST, (1) 4,000-gallon UST, and (1) 2,000-gallon UST.
• Air test tanks, set precast deadmen, set tanks, install anchor straps and secure.
• Backfill with pea rock, trench from tanks to Fuel Island. Set tank sumps.
• Pipe (3) 2” FRP vent lines from tanks. Vents above grade to be 2” steel pipe; pipe (3) new fill assemblies (Diesel, Gas and DEF). Apply corrosion protection to all underground metal components.
• Run 4” corrugated chase pipe. Pull 2” DW Fiberglass from tanks to dispenser sumps.
• Pipe 2” LCX to each DEF dispenser creating a closed loop for recirculation. ***In Minnesota you cannot pipe DEF without either heating the line or putting in a recirculation system. We have figured recirculation and this requires the TLS450+ to have the necessary components to do so.
• Pipe 2” LCX to (1) single sided diesel dispenser, (1) master/satellite diesel dispenser, and (1) single sided diesel satellite dispenser.
• Per drawing F6.0 detail G. Pipe and plumb DEF fill station. Route piping thru 6” PVC piping chase. At exit point in concrete use spray foam and self-leveling caulk.
• Pipe 2” LCX to (1) dual sided gasoline dispenser.
• Pipe (3) gauge risers, pipe (3) interstitial risers, set spillers, and manways.
• Set (4) SS islands 48” x 72” 13” 304L grade /#4 polish. Set dispenser sumps and make final connections.
• Infill islands.
• Auger and set (12) 8” bollards. Install sleeve covers G59-3456M.
• Set (4) Gilbarco Encore 500’s. NPA, NPB, NAO and NP5.
• Prep site for concrete
• Pour 8” tank pad 24’ x 75’.
• Pour fuel island approach lanes 43’ x 40’.
• Set new kiosk, set new J.E Adams 9225 Vacuum.
• Remove existing tank. Using existing wiring mount the new TLS-450 w/printer. Install all probes and sensors. In parts room install new FSC 3000.
• Update COPT software to Phoenix. Set new COPT in Kiosk.
• Fabricate and install new collection boxes on the canopy. Run (4) new downspouts.
• Provide Training. Startup system and place in service.
Bulk Fluids
Description
• From fuel island trench 101’ to building. Run 4” flexworks access chase pipe.
• Transition from piping to (3) hydraulic hoses. Pull from building through 4” chase pipe to Fuel Island. Make final connections.
• Run 1” copper water line in same trench next to 4” chase pipe. Stub up and connect to water hydrant at Fuel Island.
(Location TBD).
• Erect 6’ by 6” steel pole.
• Mount (3) Graco reels. (Anti-freeze/washer fluid, Air and Oil).
• Make final connections.
• Install Meters.
• Check existing pumps to make sure they can handle the volume and distance to the fuel island.
• Pour concrete over trench 101’