Pump & Meter Service, Inc.
Hopkins, MN 55343
Featured Project Return to Projects List
City of Eden Prairie
Project Information
- Project Location:
- Eden Praire, MN
- Approx Contract:
- $100,000
- Status:
- Completed - Oct 2019
- Structure Type:
- Government
References
- Owner:
- City of Eden Prairie
Scope Of Work
Notify Gopher 1.
Remove (2) dispensers and (1) card reader of island. (Card Reader to be reused).
Demo fuel island and tank slab.
Excavate down to top of (2) UST’s.
Remove all piping, electrical, concrete and bollards. Dispose offsite.
Install new tank sumps, dispenser sumps, spillers, (8) bollards, and set manways.
Run new APT flex pipe from each tank to corresponding dispenser sumps.
Backfill, prep site for correct elevations to slope surrounding grades to the east. New Fuel Island base to be 4” higher than existing island.
Once all elevations are confirmed by engineering and the City, replace island (6’ by 36’) and fuel island approach
(30’ by 57’).
Concrete shall have #5 rebar, 2’ by 2’ on center with 3” embedment with 6” pour and high early design mix.
After concrete has cured, set (2) new Gasboy 9800 Series Dispensers.
Reset Gasboy Islander. Confirm system is back online.
Complete vent lines through canopy.
Provide necessary erosion control per (SWPPP).
Paint Bollards.
Start up and place in service.